Marking an Activity Done

When you complete an activity you should always mark it done. Once an activity is marked done, it will no longer appear in activity lists reminding you to perform it. You can view the completed activity on the Activities Summary screen and from the Activities tab of the associated record.

If you marked on activity done and want to reverse this, you can mark the activity as "incomplete". See the "To undo a mark done" procedure below.

To mark a single activity done:

This procedure describes how to mark an individual activity done. For instructions on marking multiple activities done, see the "Performing Mass Actions on Activities" topic.

  1. If you are working with activities from the:

  2. Click the mark_done_icon.gif icon beside the activity you want to mark done.

    If the activity is a parent activity or an activity linked to a listing or closing, proceed to step 3. Otherwise, skip this step.

  3. If you are working with a:

To undo a mark done:

Note: You can only mark an individual activity as "incomplete".

  1. If you are working with activities from the:

  2. If desired, specify filter options to find the activity you want to mark as "incomplete". More Info:triangle.gif

  3. Click the Undo Mark Done undo_mark_done.jpg icon adjacent to the activity you want to mark "incomplete".

The activity is marked "incomplete" and will appear in activity lists reminding you to perform it.